1) 36 men can complete a work in 18 days. in how many days will 54 men can complete the same work?

Explanation:

Less men means more days ( Inverse proportion) 54 : 36 :: 18 : x => x = (36 x 18) / 54 = 36 / 3 = 12 Required number of days = 12, with 54 people working on it